Works on our Putney Embankment Foreshore site are progressing well. We are reinstating the cycleway that runs along Lower Richmond Road. To ensure this work can be carried out safely parking continues to be suspended in the bays outside the main Tideway site until the end of April 2023.
As part of our ongoing activities the team are installing balustrades, continuing with paving works and undertaking some minor excavation work adjacent to Putney Pier. These works are expected to be completed at the end of May.
We are also continuing with the reinstatement of the river wall that was removed to make way for the temporary slipway. Sheet pile removal will restart in May 2023 using excavator mounted equipment. We are removing the concrete blocks that formed the slipway which will then expose all of the metal that also needs to be removed. This work is expected to finish at the end of May.
If you have any questions about our Putney site call our helpdesk on 08000 30 80 80 or email [email protected].