This site is made up of two parts; a main site (which includes Whiffin Wharf, Hurlingham Wharf, Carnwath Road Industrial Estate and an area of the River Thames foreshore) and a small highways work site.

While there is no combined sewer overflow being intercepted at this site, it will be used to drive the main tunnel to Acton Storm Tanks and receive the main tunnel from Kirtling Street. It would also receive the Frogmore connection tunnel driven from Dormay Street. 

Works update

We have commenced welding works on our piles at the river wall. These are required to absorb and reduce any potential impact from our barges once the tunnelling begins. These works will run for approximately 8 weeks.

On occasion, due to tidal conditions, we may need to complete these works outside our core hours and have been granted permission to work between 06:00 – 22:00 Monday to Friday as required. Read More

With the shaft excavation near completion, we need to carry out a base plug pour which is essentially pouring a large amount of concrete down to the bottom of the shaft. This will help support the shaft before the tunnelling. 

The concrete pour will start around 7pm on Friday 7 September and may take up to 96 hours to complete. Once we start it is essential the concrete is poured continuously, therefore concrete lorries will be arriving on a 24-hour basis until the pour is completed. Read More

Want to know more or get involved?

There are lots of ways to find out what’s happening at this site, you can:

  • Call our 24 hour Tideway Helpdesk 08000 30 80 80 or email [email protected].
  • Take a moment to read the latest updates on the noticeboards on our hoardings.
  • Visit Tideway's Community Information Centre at Carnwath Road, the first Tuesday of the month, 3pm – 7pm. Our team will be able to answer your questions and talk about the work.
  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected]. Meeting details will be emailed, published online and on site hoardings.

Carnwath Road Riverside - Latest news

 

Hoarding Artwork

The Carnwath Road Riverside site hoarding is now bright and colourful thanks to Sulivan School. Pupils got together to create this wonderful artwork that has brightened the east section of the site.

Tideway's River Times - West

The latest issue of Tideway's new regular community newsletter, produced especially for our neighbours in the west section of the project.

River Times West - Summer 2018

Carnwath Road Riverside - Site Information

What are our working hours?

Standard working hours are 8am to 6pm Monday-Friday and 8am-12pm Saturday.  Also, there is an 1 hour mobilisation period before and after the Standard Working Hours, plus maintenance periods on Saturday 1-5pm and Sundays 10am-4pm.

How will we use the river?

We have committed to using river transport as much as possible to reduce the number of heavy goods vehicles on the roads.

For Carnwath Road Riverside we anticipate an average of two barges overall per day, and potentially a peak of four barges per day, subject to the tides, with each barge taking approximately 45 heavy goods vehicles off the road.

An anticipated daily average of 19 heavy goods vehicles will access the site. This will rise to approximately 45 per day for about 17 months during the main tunnel construction.

It is proposed that approximately two-thirds of materials will be moved by river and approximately one-third will be moved by road.

Carnwath Road Riverside - Community Liaison Working Group

The date for the next Carnwath Road Riverside CLWG will be announced soon.

17 September 2018 - CLWG Presentation

25 June 2018 - Community Liaison Working Group Minutes

25 June 2018 - CLWG Presentation 

Further minutes can be found in our Document Library.

Our community

Working in the community

Giving back to the community

Education programme

Careers and skills

Carnwath Road Riverside - How we will minimise disruption

  • There will be a noise enclosure over the tunnel drive shaft during works  
  • All static machinery and plant will be screened or enclosed
  • Hoarding will be erected on the site boundaries
  • Vehicle movements outside of standard hours will be restricted
  • Use of low level directional lighting
  • Set limits to control activities, such as noise (Section 61 approval) from LB Hammersmith & Fulham

Carnwath Road Riverside - Important site documents


Submissions to the council

We have been making a number of submissions to the London Borough of Hammersmith and Fulham as part of the consents, as we need to secure before starting different phases of work at Carnwath Road Riverside. These submissions will be available to view on the London Borough of Hammersmith and Fulham’s planning portal. Please click here to be redirected. This includes the submissions for Hammersmith Pumping Station.

If you are interested in commenting on these submissions, please ensure you respond directly to the London Borough of Hammersmith and Fulham.

The latest Air Quality and Noise reports for Carnwath Road Riverside can be found here.